Correct option is C
Given:
A can complete the work in 22 days
B can complete the work in 24 days
C can complete the work in 33 days
Formula Used:
Efficiency =
Solution:
Let Total Work = 264 units(LCM of 22, 24, 33)
A’s efficiency = = 12 units/day
B’s efficiency = = 11 units/day
C’s efficiency = = 8 units/day
Work in 3-day cycle
Day 1: A works = 12 units
Day 2: C works = 8 units
Day 3: B works = 11 units
Total in 3 days = 12 + 8 + 11 = 31 units
Now,
Time taken = 8 3 = 24 days
Remaining work = 264 - 248 = 16 units
Day 25 (A’s turn): does 12 units
Remaining: 16 - 12 = 4 units
Day 26 (C’s turn): does 8 units/day
To do 4 units => = 0.5 day
Total Time: 24 + 1 + 0.5 = 25.5 days