    Suraj completes 112\frac1{12}121​​ of a work in nine days. At this rate, how many more days will he take to complete the work?
    Question

    Suraj completes 112\frac1{12}​ of a work in nine days. At this rate, how many more days will he take to complete the work?

    A.

    90

    B.

    108

    C.

    81

    D.

    99

    Correct option is D

    Given:

    Suraj completes 112\frac{1}{12}​ of the work in 9 days..

    Solution:

    If 112 \frac{1}{12}​ work takes 9 days, then full work takes:

    Total time = 9 × 12 = 108 days

    Remaining days = 108 – 9 = 99 days

    Free Tests

    Free
    Must Attempt

    SSC GD PYP (Held on 4 Feb 2025 S1)

    languageIcon English
    • pdpQsnIcon80 Questions
    • pdpsheetsIcon160 Marks
    • timerIcon60 Mins
    languageIcon English
    Free
    Must Attempt

    Hindi Section Test 1

    languageIcon English
    • pdpQsnIcon20 Questions
    • pdpsheetsIcon40 Marks
    • timerIcon12 Mins
    languageIcon English
    Free
    Must Attempt

    SSC GD Constable Full Mock Test 1

    languageIcon English
    • pdpQsnIcon80 Questions
    • pdpsheetsIcon160 Marks
    • timerIcon60 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘SSC GD’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    368k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow