Correct option is B
Given:
Time taken by Ravi to complete the job = 48days
Kiran is 60% more efficient than Ravi
Formula Used:
Let total work be 1.
Then work done 1 day =
Work done = Efficiency of each worker Time
Solution:
Ravi’s one day work =
Then Kiran’s is 60% more efficient then Kiran’s one day work =
Then work done by both Ravi and Kiran together in one day =
Total time required by both Ravi and Kiran working together =days
Hence, option(b) is correct
Alternative Method:
Let the efficiency of Ravi be x
Then efficiency of Kiran will be = x + 60% of x = 1.6x
Total efficiency of both Ravi and Kiran working together = x + 1.6x = 2.6x
Total work = Total days required by Ravi Efficiency = 48x
Time required by both Ravi and Kiran working together =days