Correct option is D
Given:
P can complete a task in 10 days working 6 hours a day.
Q can complete the same task in 9 days working 10 hours a day.
Both P and Q work together working 6 hours a day.
Formula used:
Work done in 1 hour =
Solution:
Work done by P in 1 hour:
=>
Work done by Q in 1 hour:
=>
Work done by P and Q together in 1 hour:
=>
=>
=>
=>
Time taken by P and Q together working 6 hours a day:
=>
=>
=> 6 days