hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    ​P and Q alone can complete a piece of work in 9 days and 12 days, respectively. In how many days will the work be completed if they work on alternate
    Question

    ​P and Q alone can complete a piece of work in 9 days and 12 days, respectively. In how many days will the work be completed if they work on alternate days starting with Q ?​

    A.

    101310\frac{1}{3}​​

    B.

    115611\frac{5}{6}​​

    C.

    111311\frac{1}{3}​​

    D.

    105610\frac{5}{6}​​

    Correct option is A

    Given:

    P  can finish task in 9 days

    Q can finish task in 12days

    Formula Used:

    Let total work be 1.

    Then work done 1 day =1Total time to work\frac{1}{Total\ time\ to\ work}​​

    Solution:

    P’s one day’s work = 19\frac{1}{9}​​

    Q’s one day’s work = 112\frac{1}{12}​​

    P and Q’s one pair of day’s work =  19+112=4+336=736\frac{1}{9} + \frac{1}{12} = \frac{4+3}{36} = \frac{7}{36}​​

    Total work = 36 and one pair of day is 7

    Pair of days required to complete the work = 736×5=3536\frac{7}{36} \times 5 = \frac{35}{36}​​

    Total days required to complete 3536\frac{35}{36}​ of work = 5×25 \times 2 = 10 days

    Work remaining = 13536=1361 - \frac{35}{36} = \frac{1}{36}​​

    Work was started with Q hence when Q started working on 11th day he worked for:

    =136112=13= \frac{\frac{1}{36}}{\frac{1}{12}} = \frac{1}{3}​​

    Hence total time required = 10+13=1013days10 + \frac{1}{3} =10\frac{1}{3} days​​

    Alternative Method:

    Total Work = Efficiency ×\times​ Time

    Total Work = LCM of 9 and 12  =36

    Efficiency of P =369\frac{36}{9} = 4 units per day.

    Efficiency of Q = 3612\frac{36}{12} = 3 units per day

    Efficiency of P and Q together in one pair of days working alternatively = 4 + 3 =7 units per day

    Time taken by P and Q together to complete the work = 367=5+17days\frac{36}{7} = 5 + \frac{1}{7}days​​

    Work left = 1

    Time required by Q  = 13\frac{1}{3}

    Hence, total time required = 5×2+13=1013days5 \times 2 + \frac{1}{3} =10\frac{1}{3} days​​

    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    CBT-1 General Awareness Section Test 1

    languageIcon English
    • pdpQsnIcon40 Questions
    • pdpsheetsIcon30 Marks
    • timerIcon25 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB Group D’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow