Correct option is A
Given:
P can finish task in 9 days
Q can finish task in 12days
Formula Used:
Let total work be 1.
Then work done 1 day =
Solution:
P’s one day’s work =
Q’s one day’s work =
P and Q’s one pair of day’s work =
Total work = 36 and one pair of day is 7
Pair of days required to complete the work =
Total days required to complete of work = = 10 days
Work remaining =
Work was started with Q hence when Q started working on 11th day he worked for:
Hence total time required =
Alternative Method:
Total Work = Efficiency Time
Total Work = LCM of 9 and 12 =36
Efficiency of P = = 4 units per day.
Efficiency of Q = = 3 units per day
Efficiency of P and Q together in one pair of days working alternatively = 4 + 3 =7 units per day
Time taken by P and Q together to complete the work =
Work left = 1
Time required by Q =
Hence, total time required =