Correct option is C
Given:
Kartik can do the work in 4 hours
Ishan can do it in 20 hours
All three together completed the work in 2 hours
Solution:
Kartik work rate =
Ishan rate =
Kartik + Ishan + Krish combined rate =
Let Krish’s rate be Then:
Thus, Ishan time to complete the work is 5 hours
Alternate Solution:
total work = LCM of 4, 20, and 2 = 20 units
Kartik's rate = = 5 units/hour
Ishan's rate = = 1 unit/hour
All three together = = 10 units/hour
Now , Krish's rate = 10 - (5 + 1) = 4 units/hour
So, time taken by Krish alone = = 5 hours