Correct option is D
Given:
Number of workers (W1) = 25
Time taken (T1) = 10 days
Number of workers (W2) = 20
Formula Used:
W1 ×T1 = W2 ×T2
Solution:
25 ×10 = 20 ×T2
T2 = (25 ×10) / 20 = 12.5 = 25/2 days
Thus, it will take 12.5 days for 20 workers to build the wall.