arrow
arrow
arrow
If 24 men can complete a piece of work in 15 days working 8 h per day, then how many men will be required to complete the same work in 10 days working
Question

If 24 men can complete a piece of work in 15 days working 8 h per day, then how many men will be required to complete the same work in 10 days working 6 h per day?

A.

32

B.

30

C.

48

D.

60

Correct option is C

Given:

Number of men = 24

Time taken = 15 days

Hours worked per day = 8 hours

New time to complete the work = 10 days

New hours worked per day = 6 hours

Formula Used:

Work = Men × Hours per day × Time in days

Solution:
First, calculate the total work done in the initial situation:

Work =24×8×15=2880 man-hours 24 \times 8 \times 15 = 2880 \, \text{man-hours}

Now, let x be the number of men required to complete the work in 10 days, working 6 hours per day. The total work will still be 2880 man-hours, so:

x×6×10=2880x \times 6 \times 10 = 2880​​

60x = 2880

x =288060=48 \frac{2880}{60} = 48

48 men will be required to complete the work in 10 days working 6 hours per day.

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB NTPC’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
353k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow