Correct option is C
Given:
Number of men = 24
Time taken = 15 days
Hours worked per day = 8 hours
New time to complete the work = 10 days
New hours worked per day = 6 hours
Formula Used:
Work = Men × Hours per day × Time in days
Solution:
First, calculate the total work done in the initial situation:
Work =
Now, let x be the number of men required to complete the work in 10 days, working 6 hours per day. The total work will still be 2880 man-hours, so:
60x = 2880
x =
48 men will be required to complete the work in 10 days working 6 hours per day.