If 12 men and 6 boys can do a work in 4 days and 4 men and 14 boys can do the same work in 8 days, find the ratio of efficiency of a man to that of a
Question

If 12 men and 6 boys can do a work in 4 days and 4 men and 14 boys can do the same work in 8 days, find the ratio of efficiency of a man to that of a boy. 

A.

2 : 11

B.

2 : 5

C.

3 : 7

D.

11 : 2

Correct option is D

Given:
12 men and 6 boys can complete the work in 4 days.
4 men and 14 boys can complete the work in 8 days. 
Formula Used: 
Total Work = Number of Workers × Efficiency × Time. 
Solution:
Let man be denoted as m and boys be denoted as b
(12m + 6b) × 4 = (4m + 14b) × 8.
 (12m + 6b) = (4m + 14b) × 2
12m + 6b= 8m + 28b.
4m = 22b
mb=112\frac{m}{b} =\frac{11}{2}​​
So required ratio is 11 : 2 ​

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB JE’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow