Correct option is B
Given:
A works twice as fast as B.
A and B together can finish the job in 12 days.
Formula Used:
Work Rate of A and B Together,=Ttogether1=Work Rate of A+Work Rate of B
Solution:
Let Tbbe the time taken by B alone to complete the job.
Then,
A’s time = 2TB
Now,
121=TB2+TB1=TB3
121=TB2+TB1=TB3
TB=3×12=36days
Thus B will take 36 days to finish the job alone.