Correct option is D
Given:
Initial number of labours = 8
Total time to complete the work by 8 labours = 16 days
They worked for 2 days
Additional labours joined = 8
Total labours after 2 days = 8 + 8 = 16
Formula Used:
Work done = Number of labours × Number of days
Solution:
Total work = 8 labours × 16 days = 128
Work done in first 2 days by 8 labours = 8 × 2 = 16
Remaining work = 128 − 16 = 112
Now, 16 labours are working.
Time required = = 7 days
So, the remaining work will be finished in 7 days.
Thus, the correct answer is (d).