Correct option is A
Given:
A man completes work in 15 days by working 4 h per day for 5 days, 5 h per day for 5 days, and 6 h per day for 5 days.
Formula Used:
where and are numbers of men, and are the numbers of days, and are numbers of hours.
we can only use the term given in the question.
Solution:
Let the efficiency of 1 man be 1 unit
According to the question.
Total work = 5 × 4 + 5 × 5 + 5 ×6
Total work = 75 units
After an hour break = 8 hours - 30 minutes
=> After an hour break = 7 hours 30 minutes.
Now, Total work = 7.5 × no of days
=> 75 = 7.5 × D
=> D = 10 days