A can finish a work in 16 days, and B can do the same work in 12 days. With the help of C, they completed the work in 4 days. In how many days can C a
Question

A can finish a work in 16 days, and B can do the same work in 12 days. With the help of C, they completed the work in 4 days. In how many days can C alone do the same work?

A.

48/7

B.

48/5

C.

38/7

D.

43/7

Correct option is B

Given:

A can do the work in 16 days

B can do the work in 12 days

A + B + C together finish the work in 4 days

Formula Used:

Work per day = Total WorkDays taken\frac{\text{Total Work}}{\text{Days taken}}​​

Solution:

Assume the total work = LCM of 16, 12, and 4 = 48 units

A’s 1-day work = 4816 \frac{48}{16}​ = 3  units/day

B’s 1-day work = 4812 \frac{48}{12}​ = 4 units/day

A + B + C together do = 484 \frac{48}{4}​ = 12 units/day

Now compute C’s 1-day work:

C's work/day = 12 - (A + B) = 12 - (3 + 4) = 5 units/day

Now, C alone would take: 

485\frac{48}{5}​days

Free Tests

Free
Must Attempt

SSC GD PYP (Held on 4 Feb 2025 S1)

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Hindi Section Test 1

languageIcon English
  • pdpQsnIcon20 Questions
  • pdpsheetsIcon40 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

SSC GD Constable Full Mock Test 1

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC GD’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow