A can do a work in 4 days and B in 12 days. If they work on it together for 2 days, then the fraction of the work that will be left is:
Question

A can do a work in 4 days and B in 12 days. If they work on it together for 2 days, then the fraction of the work that will be left is:

A.

2/3

B.

2/5

C.

1/3

D.

1/5

Correct option is C

Given:

A can complete the work in 4 days, and B can complete it in 12 days. We need to find the fraction of the work left after they work together for 2 days.

Solution:

Work done by A in 1=  day 14\frac{1}{4}​​

Work done by B in 1 day = 112\frac{1}{12}​​

Work done by A and B together in 1 day =14+112\frac{1}{4} + \frac{1}{12}​​

Work done by A and B together in 1 day = (3+1)12=13\frac{(3+1)}{12} = \frac{1}{3}​​

Work done by A and B together in 2 days = 2×13=232\times \frac{1}{3} = \frac{2}{3}​​

Fraction of work left = 123=131 - \frac{2}{3} = \frac{1}{3}​​

Therefore, the fraction of the work that will be left is 13.\frac{1}{3}.​​

Free Tests

Free
Must Attempt

SSC GD PYP (Held on 4 Feb 2025 S1)

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Hindi Section Test 1

languageIcon English
  • pdpQsnIcon20 Questions
  • pdpsheetsIcon40 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

SSC GD Constable Full Mock Test 1

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC CGL Tier I’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow