Correct option is C
Given:
A can do the work in 12 days.
B can do the work in 20 days.
A, B, and C together can complete the work in 3 days.
Concept Used:
Work done by a person in a day =
Solution:
A can do the work in 12 days, so the work rate of A is:
Rate of A =
B can do the work in 20 days, so the work rate of B is:
Rate of B =
A, B, and C together can complete the work in 3 days, so their combined work rate is:
Rate of A, B, and C =
The combined work rate of A, B, and C is the sum of the individual work rates of A, B, and C.
Thus, we can express C's work rate as:
Rate of C =
C alone can do the work in 5 days.
Alternate Method:
Assume, total work = 60 unit
Efficiency of A =
Efficiency of B =
Efficiency of A + B + C =
Efficiency of C = 20 - 5 - 3 =12
Time taken by C = = 5