    A,B and C can complete a task in 36 , 54 and 72 days respectively. Together they started the task but A left 8 days before the completion of the task
    Question

    A,B and C can complete a task in 36 , 54 and 72 days respectively. Together they started the task but A left 8 days before the completion of the task while B left 12 days before the completion. the number of days for which C worked is:

    A.

    24

    B.

    28

    C.

    40

    D.

    32

    Correct option is A

    Given:

    A, B, and C can complete a work in 36, 54, and 72 days respectively.

    A, B, and C started the task together,

    A left 8 days before the completion of the work.

    B left 12 days before the completion of the work.

    Formula used:

    Work = Time × Efficiency

    Solution:

    The efficiency of A = 136\frac{1}{36}​​

    The efficiency of B =  154\frac{1}{54}​​

    The efficiency of C = 172\frac{1}{72}​​

    Suppose work is completed in x days.

    Work done by A = x836\frac{x-8}{36}​​

    Work done by B = x1254\frac{x-12}{54}​​

    Work done by C = ​x72\frac{x}{72}

    Total work done by A, B and C = x836+x1254+x72\frac{x-8}{36} + \frac{x-12}{54} +\frac{x}{72}​​

    (6x48+4x48+3x)216=1 13x=216+96 x=31213=24 days\begin{aligned}&\implies \frac{(6x - 48 + 4x - 48 + 3x)}{216} = 1 \\&\implies 13x = 216 + 96 \\&\implies x = \frac{312}{13} = 24 \, \text{days}\end{aligned}​​

    ∴ The number of days for which C worked is 24.  

    Alternate Solution:   

    If A has worked for 8 more days then work done by A in 8 days = 6×8=486\times 8 = 48​​

    If B has worked for 12 more days then work done by B in 12 days =4×12=484 \times 12 = 48​​

    Total Work done = 216 + 48 + 48 = 312 

    Time taken by A, B and C to complete this work = 31213=24\frac{312}{13} = 24 days.

    Hence, Time taken by C to complete the work in 24 days.

    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    CBT-1 General Awareness Section Test 1

    languageIcon English
    • pdpQsnIcon40 Questions
    • pdpsheetsIcon30 Marks
    • timerIcon25 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB NTPC’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow