Correct option is C
Given:
A and B can together complete a task in 16 days
They started a task together and after 4 days A leave, B takes 24 days to finish the rest of the task.
Formula Used:
Work = Time × Efficiency
Solution:
Let the efficiency of A and B be a and b respectively.
Total work = (a + b) × 16
Work done by A and B together = 4 × (a + b)
Remaining work done by B = 24 × b
Total work = work done by A + B together in 16 days = work done by ( A + B) × 4 + work done by B in 24 days
So,
4 × (a + b) + 24 × b = (a + b) × 16
a = b
Then, time taken by B alone to finish work = = 32 days.