Correct option is C
Given:
A and B can complete a work in 20days
B and C can complete the work in 12days
A and C can complete the work in 15 days
Formula Used:
Let total work be 1.
Then work done 1 day =Total time to work1
Solution:
A and B’s one day work =A1+B1=201 ….(1)
B and C’s one day work =B1+C1=121 …(2)
A and C’s one day work= A1+C1=151 ….(3)
Adding all the equations we get
2(A1+B1+C1)’s one day work: =201+121+151=603+5+4=6012=51
(A+B+C)’s one day work = 101
A,B and C can complete the work in = 1011 = 10 days