Correct option is C
Given:
A alone completes the work in 15 days.
So, A's 1-day work =
B alone completes the work in 30 days.
So, B's 1-day work =
They work on alternate days, starting with A.
Concept Used:
In 2 days, work done = A’s 1-day work + B’s 1-day work.
We continue this cycle until the work is completed.
Solution:
=
So, in 2 days, they complete of the work.
Since total work is 1, we calculate the number of full 2-day cycles:
Each cycle takes 2 days, so:
10×2=20 days
Option (C) is right.