Correct option is D
Given:
80 men can construct a footpath in 100 days. Work has to be finished in 25 days.
Formula Used:
Work = Men × Days
Solution:
Total work = 80 × 100 = 8000 man-days
Work must be done in 25 days
Required men = = 320
Additional men needed = 320 − 80 = 240