    50 men can do a piece of work in 12 days. The number of men required to complete the same work in 50 days is:
    Question

    50 men can do a piece of work in 12 days. The number of men required to complete the same work in 50 days is:

    A.

    12

    B.

    11

    C.

    19

    D.

    15

    Correct option is A

    Given:

    50 men can complete the work in 12 days.

    The same work needs to be completed in 50 days.

    Formula Used:

    For equal work

    M1×D1=M2×D2M_1 \times D_1 = M_2 \times D_2​​

    Solution:

    M1=50M_1 = 50 ​​ and D1=12D_1​ = 12​​

    M2=?M_2 = ?​ and D2=50 D_2 = 50​​

    50×12=M2×5050 \times 12 = M_2 \times 50​​

    M2=50×1250=12M_2 = \frac{50 \times 12}{50} = 12​​

    12 men are required to complete the work in 50 days.

    thus , the correct answer is 12 .

    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    CBT-1 General Awareness Section Test 1

    languageIcon English
    • pdpQsnIcon40 Questions
    • pdpsheetsIcon30 Marks
    • timerIcon25 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB JE CBT-I’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow