50 men can do a piece of work in 12 days. The number of men required to complete the same work in 50 days is:
Question

50 men can do a piece of work in 12 days. The number of men required to complete the same work in 50 days is:

A.

12

B.

11

C.

19

D.

15

Correct option is A

Given:

50 men can complete the work in 12 days.

The same work needs to be completed in 50 days.

Formula Used:

For equal work

M1×D1=M2×D2M_1 \times D_1 = M_2 \times D_2​​

Solution:

M1=50M_1 = 50 ​​ and D1=12D_1​ = 12​​

M2=?M_2 = ?​ and D2=50 D_2 = 50​​

50×12=M2×5050 \times 12 = M_2 \times 50​​

M2=50×1250=12M_2 = \frac{50 \times 12}{50} = 12​​

12 men are required to complete the work in 50 days.

thus , the correct answer is 12 .

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB JE CBT-I’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow