Correct option is B
Given:
44 men can do a piece of work in 48 days.
Concept used:
The concept of man-days.
Total work= Number of men× Number of days× Efficiency
Solution:
Total work=44 men×48 days=2112 man−days.
Let the required number of men be xxx to complete the same work in 8 days.
The total work remains the same (2112 man-days)
x×8=2112
x=82112
x=264 men
The number of men required to complete the work in 8 days is 264 men.