4 boys or 7 girls can complete a piece of work in 18 days. How many days will 12 boys and 21 girls together take to complete this job?
Question

4 boys or 7 girls can complete a piece of work in 18 days. How many days will 12 boys and 21 girls together take to complete this job?


A.

3 days

B.

4 days

C.

7 days

D.

2613\tfrac{1}{3} days​

Correct option is A

Given:

4 boys or 7 girls can complete a piece of work in 18 days. 

Formula Used:

Total work = Number of workers × Efficiency of each worker × Days to complete the work

Solution:

Let the efficiency of each boy and girl be B and G respectively.

According to the concept,

4B = 7G

BG=74\frac{B}{G} = \frac{7}{4}​​

So, the efficiencies of each boy and girl be 7k and 4k respectively. (k = constant)

Total work = (4 × 7k × 18) units

Now, to complete the job, 12 boys and 21 girls together will take

=> (4 × 7k × 18) ÷ (12 × 7k + 21 × 4k)

=> 3 days


Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB NTPC’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow