20 men can do a work in 24 days and 24 women can do the same work in 48 days. 20 men started the work and after 12 days all 20 men left the work. Find
Question



20 men can do a work in 24 days and 24 women can do the same work in 48 days. 20 men started the work and after 12 days all 20 men left the work. Find how many women are required to complete the remaining work in 8 days?

A.

36

B.

48

C.

64

D.

72

E.

60

Correct option is D


Let one day efficiency of a man be x unit/day and a woman is y unit/day
ATQ, 20x ×24 = 24y ×48
20x = 48x
x : y = 12 : 5
Now let, x = 12u and y = 5u
Total work = 20× 12u ×24 = 5760u unit
Total work done by 20 men in 12 days =20× 12u ×12 = 2880u unit
Remaining work = 5760u – 2880u = 2880u unit
Required women = 2880u/(5u×8) = 72

Free Tests

Free
Must Attempt

SBI Clerk Prelims Full Mock Test-01

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

SBI Clerk Prelims Full Mock Test-02

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

SBI Clerk Prelims Reasoning Section Test 04

languageIcon English
  • pdpQsnIcon35 Questions
  • pdpsheetsIcon35 Marks
  • timerIcon20 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SBI Clerk’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
390k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘SBI Clerk’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
390k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow