arrow
arrow
arrow
16 men can finish a piece of work in 8 days while 20 women and 4 men can do it in 16 days. In how many days can 10 women complete the entire work by t
Question

16 men can finish a piece of work in 8 days while 20 women and 4 men can do it in 16 days. In how many days can 10 women complete the entire work by themselves?

A.

40 days

B.

60 days

C.

64 days

D.

48 days

Correct option is C

Given:

16 men can finish the work in 8 days.

20 women and 4 men can finish the work in 16 days.

We need to find how many days 10 women would take to complete the work.

Formula Used:

Total work = Number of workers × Rate of work × Time

Solution:

Total work done = 1

16×8×m=1 m=112816 \times 8 \times m = 1 \\ \ \\m = \frac{1}{128}​​

So, each man does 1128\frac{1}{128}​ of the work per day.

20 women and 4 men complete the work in 16 days. Hence, the total work is:

(20×w+4×m)×16=1(20 \times w + 4 \times m) \times 16 = 1​​

Substitute m =1128:= \frac{1}{128}:​​

(20×w+4×1128)×16=1(20 \times w + 4 \times \frac{1}{128}) \times 16 = 1​​

(20w+4128)×16=1(20w + \frac{4}{128}) \times 16 = 1​​

(20w+132)×16=1(20w + \frac{1}{32}) \times 16 = 1​​

320w+12=1320w + \frac{1}{2} = 1​​

320w=112=12320w = 1 - \frac{1}{2} = \frac{1}{2}​​

w=1640w = \frac{1}{640}​​

So, each woman does 1640\frac{1}{640}​ of the work per day.

Now, 10 women will complete the work, and the total work done by them per day is:

10×w=10×1640=10640=16410 \times w = 10 \times \frac{1}{640} = \frac{10}{640} = \frac{1}{64}​​

Therefore, the number of days required for 10 women to complete the work is:

Time =1164=64 days= \frac{1}{\frac{1}{64}} = 64 \text{ days}

10 women will complete the work in 64 days.

Alternate Method:

M1D1H1W1=M2D2H2W2\frac{M_1D_1H_1}{W_1}=\frac{M_2D_2H_2}{W_2}

M = Man , D = Days , H = Hours , W= Work / Wages

16 M×8\times 8 = ( 20W + 4M )×16\times 16

128 M = 320 W + 64 M

64 M = 320 W

MW=51\frac MW= \frac 51

Efficiency of Man = 5, Efficiency of Women =1

Total Work = 16 M×8\times 8 = 16×5×8\times 5 \times 8 = 640

Then, 640 = 10 W + D

640 = 10×1\times 1 + D

D = 64010\frac {640}{10} = 64 days​

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB NTPC’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow