Correct option is C
Given:
16 men can finish the work in 8 days.
20 women and 4 men can finish the work in 16 days.
We need to find how many days 10 women would take to complete the work.
Formula Used:
Total work = Number of workers × Rate of work × Time
Solution:
Total work done = 1
So, each man does of the work per day.
20 women and 4 men complete the work in 16 days. Hence, the total work is:
Substitute m
So, each woman does of the work per day.
Now, 10 women will complete the work, and the total work done by them per day is:
Therefore, the number of days required for 10 women to complete the work is:
Time
10 women will complete the work in 64 days.
Alternate Method:
M = Man , D = Days , H = Hours , W= Work / Wages
16 M = ( 20W + 4M )
128 M = 320 W + 64 M
64 M = 320 W
Efficiency of Man = 5, Efficiency of Women =1
Total Work = 16 M = 16 = 640
Then, 640 = 10 W + D
640 = 10 + D
D = = 64 days