Correct option is B
Given:
14 men can complete the task in 9 days.
16 women can complete the task in 7 days.
We are asked to find how many days 6 men and 8 women can complete the same task.
Concept Used:
The rate of work is the reciprocal of the time taken to complete the task.
Solution:
Rate of 1 man =14×91=1261 tasks/day
Rate of 6 men =6×1261=1266=211 tasks/day
Rate of 1 woman = 16×71=1121 tasks/day
Rate of 8 women =8×1121=1128=141 tasks/day
Combined rate of 6 men and 8 women:
Combined rate =211+141=422+423=425 tasks/day
Time taken to complete 1 task:
Time taken = Combined rate1=4251=542=8.4 days
Thus, 6 men and 8 women can complete the task in 8.4 days.
Alternate Method:
W1M1D1H1=W2M2D2H2
M = Man, D = Days , H = Hours, W = Work
14M ×9= 16W ×7
WM=98
Total Work = 14 × 8 × 9 = 1008
Now,
6M + 8W= 6 × 8 + 8 × 9
= 48 + 72 = 120
Time taken = 1201008 = 8.4 days