    100 workers working 8 hours a day can dig a canal 2000 metres long in 25 days. Find the number of workers required to dig a similar canal of 2800 metr
    Question

    100 workers working 8 hours a day can dig a canal 2000 metres long in 25 days. Find the number of workers required to dig a similar canal of 2800 metres long in 32 days working 5 hours a day.

    A.

    170

    B.

    180

    C.

    175

    D.

    165

    Correct option is C

    M1×D1×H1W1=M2×D2×H2W2100×8×252000=M2×32×52800\frac{M_1 \times D_1 \times H_1}{W_1}= \frac{M_2 \times D_2 \times H_2}{W_2}\\\frac{100 \times 8 \times 25}{2000}= \frac{M_2 \times 32\times 5}{2800}

    M2M_2  = 175 MEN

    Free Tests

    Free
    Must Attempt

    SSC CGL T-I Similar Paper (Held on 12 Sep 2025 S2)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon200 Marks
    • timerIcon60 Mins
    languageIcon English
    Free
    Must Attempt

    SSC CGL T-I GA Section Test 01

    languageIcon English
    • pdpQsnIcon25 Questions
    • pdpsheetsIcon50 Marks
    • timerIcon15 Mins
    languageIcon English
    Free
    Must Attempt

    SSC CGL T-I Full Mock Test 1 (Exam Level)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon200 Marks
    • timerIcon60 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘SSC MTS’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow