The minimum number of persons required for direct ranging is 2. Similarly, the number of persons required for indirect ranging is __________.
Answer & Solution
Correct option is A

Indirect Ranging:
When the end stations between which a straight line is to be laid, are not inter-visible, then the indirect method of ranging is adopted. It is being carried out either by reciprocal method or by random line method.
As shown in the above figure station A and station B are not inter-visible, then, first of all, the two intermediate points M₁ and N₁ are located close to the chain line such that from point M₁ both N₁ and B are visible.
Similarly from N₁ both M₁ and A must be visible. Then, two ranging rods are placed at points M₁ and N₁. Then, the surveyor at M₁ signals the surveyor at N₁ to move to the new point N₂. It must be noted that the new point N₂ is in line with the line M₁B.
Similarly, the surveyor at point N₂ signals the surveyor at M₁ to move to a position M₂. It must be noted that the new point M₂ is in line with line N₂A.
Finally, the two surveyors are at points M₂ and N₂. This process is then repeated continuously until the points M and N are in line with the actual survey line AB.
After the final points, M and N are fixed, other successive points are easily fixed by direct ranging.
Hence the minimum number of persons required in indirect ranging is 2.