X1, X2 and X3 can do a work in 90, 45 and 67.5 days respectively. All three of them began the work together but X2 left 13.5 days before the completio
Question


X1, X2 and X3 can do a work in 90, 45 and 67.5 days respectively. All three of them began the work together but X2 left 13.5 days before the completion of the work. In how many days was the work completed?

A.

25 days

B.

24 days

C.

18 days

D.

27 days

Correct option is D

Given: X1, X2, X3 efficiencies: 1/90, 1/45, 1/67.5, X2 left 13.5 days before completion.
Formula Used: Work done = Efficiency × Time
Solution:
Efficiency of X1 = 1/90
Efficiency of X2 = 1/45
Efficiency of X3 = 2/135
LCM of 90, 45 & 135 is 270.
Efficiency of X1, X2 & X3 = 3, 6 & 4
Work done by X2 in 13.5 days = 6 × 13.5 = 81
Work done = 270 + 81 = 351
∴ Required number of days = 351/13 = 27 days

Free Tests

Free
Must Attempt

SSC GD PYP (Held on 4 Feb 2025 S1)

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Hindi Section Test 1

languageIcon English
  • pdpQsnIcon20 Questions
  • pdpsheetsIcon40 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

SSC GD Constable Full Mock Test 1

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC GD’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
354k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow