Correct option is A
Given:
A and B together take 24 days → Work per day = 241
B and C together take 12 days Work per day =121
A, B and C together take 6 days → Work per day =61
Solution:
A1+B1=241
B1+C1=121
A1+B1+C1=61
(A1+B1+C1)−(B1+C1)=61−121=121
A1=121
Now subtract the first from the third:
(A1+B1+C1)−(A1+B1)=61−241=81
C1=81
So,
A1+C1=121+81=242+3=245
Therefore,
A and C together take =524 days
Alternate Method:
Efficiency of ( A + B + C ) = 4
Efficiency of A = 4 - 2 =2
Efficiency of B = 1 - 2 = -1
Efficiency of C = 4 - 1 = 3
A and C together take =3+224 days=524 days