arrow
arrow
arrow
The primary difference between CPM and PERT is that:
Question

The primary difference between CPM and PERT is that:

A.

PERT has one time estimate and CPM has three time estimates

B.

PERT has two time estimates and CPM has three time estimates

C.

PERT has three time estimate and CPM requires only one time factor for each activity

D.

PERT makes the assumption that activities time are known with certainty and CPM employs three estimates to compute expected values

Correct option is C

Introduction:

The primary difference between Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) lies in their approach to time estimation and project scheduling:

  1. PERT (Program Evaluation and Review Technique):

    • Used for projects where activity durations are uncertain.

    • Uses three-time estimates for each activity to incorporate uncertainty:

      • Optimistic time (O): Minimum possible time required.

      • Most likely time (M): Time taken under normal conditions.

      • Pessimistic time (P): Maximum possible time required.

    • These estimates help calculate the expected time (TE) using the formula:

      Expected Time (TE) = (Optimistic Time + 4 × Most Likely Time + Pessimistic Time) ÷ 6

    • PERT follows a probabilistic approach, making it suitable for R&D and new product development projects.

  2. CPM (Critical Path Method):

    • Used for projects where activity durations are deterministic (known with certainty).

    • Uses only one-time estimate per activity.

    • Based on cost optimization, CPM helps determine the critical path to minimize project duration.

    • CPM is widely used in construction, production, and engineering projects.

      Information Booster:

  • PERT is event-oriented, meaning it focuses on when events occur in a project timeline.

  • CPM is activity-oriented, meaning it focuses on the time and cost required for each activity.

  • PERT is best suited for unpredictable, non-repetitive projects, such as research and development.

  • CPM is best for repetitive, predictable projects, such as construction or manufacturing.

  • PERT does not focus on cost, whereas CPM integrates time and cost analysis.

  • Both methods use network diagrams to represent project activities and dependencies.

    Additional Knowledge:

(a) PERT has one time estimate and CPM has three time estimates.
Incorrect:

  • PERT does not use a single time estimate; instead, it uses three-time estimates (Optimistic, Most Likely, and Pessimistic).

  • CPM does not use three-time estimates; it uses only one deterministic time estimate for each activity.

(b) PERT has two time estimates and CPM has three time estimates.
Incorrect:

  • PERT does not use two-time estimates; it uses three (Optimistic, Most Likely, Pessimistic).

  • CPM does not use three-time estimates; it relies on a single fixed time estimate for each task.

(d) PERT makes the assumption that activity times are known with certainty, and CPM employs three estimates to compute expected values.
Incorrect:

  • PERT assumes uncertainty and uses three estimates, not fixed values.

  • CPM does not use three-time estimates; it assumes certain and fixed time durations for activities.

Free Tests

Free
Must Attempt

Basics of Education: Pedagogy, Andragogy, and Hutagogy

languageIcon English
  • pdpQsnIcon10 Questions
  • pdpsheetsIcon20 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

UGC NET Paper 1 Mock Test 1

languageIcon English
  • pdpQsnIcon50 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Basics of Education: Pedagogy, Andragogy, and Hutagogy

languageIcon English
  • pdpQsnIcon10 Questions
  • pdpsheetsIcon20 Marks
  • timerIcon12 Mins
languageIcon English
test-prime-package

Access ‘UGC NET Management’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
353k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow