Correct option is D
Given:
P can complete the work in 9 days.
Q can complete the work in 18 days.
R can complete the work in 12 days.
Solution:
P's rate = 19\frac{1}{9}
Q's rate =
R's rate =
Total Work Done in One Cycle (3 days):
Work done in 1 cycle =
Work done in 1 cycle =
Work done in 1 cycle =
Since 14\frac{1}{4} of the work is done in one cycle, so
it will take 4 cycles to complete the whole work.
Now,
1 cycle takes 3 days,
The, total time to complete the work = 4cycles×3days/cycle=12days4 \, \text{cycles} \times 3 \, \text{days/cycle} = 12 \, \text{days}4cycles×3days/cycle=12days.
The total time required to complete the work in this manner is 12 days.
P′srate+Q′srate+R′srateP's \, \text{rate} + Q's \, \text{rate} + R's \, \text{rate}Ps′rate+Qs′rate+Rs′rateP'_srate+Q'_srate+R'_sratePs′rate+Qs′rate+Rs′rate