    P can do some work in 4 hours. Q and R together can finish it in 3 hours while P and R can doit in 2 hours. How long will Q take to complete it, if he
    Question

    P can do some work in 4 hours. Q and R together can finish it in 3 hours while P and R can doit in 2 hours. How long will Q take to complete it, if he works alone?

    A.

    8 hours

    B.

    10 hours

    C.

    12 hours

    D.

    15 hours

    Correct option is C


    Work done by p in one hour = 1/4
    Work done by Q and R in one hour = 1/3
    Work done by P and R in one hour = 1/2
    Work done by R in one hour = 1/2- 1/4= 1/4
    Work done by Q in one hour = 1/3- 1/4= 1/12
    Therefore, time taken by Q to complete the work = 12 hours.

    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    CBT-1 General Awareness Section Test 1

    languageIcon English
    • pdpQsnIcon40 Questions
    • pdpsheetsIcon30 Marks
    • timerIcon25 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB JE CBT-I’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow