P can do some work in 4 hours. Q and R together can finish it in 3 hours while P and R can doit in 2 hours. How long will Q take to complete it, if he
Question

P can do some work in 4 hours. Q and R together can finish it in 3 hours while P and R can doit in 2 hours. How long will Q take to complete it, if he works alone?

A.

8 hours

B.

10 hours

C.

12 hours

D.

15 hours

Correct option is C


Work done by p in one hour = 1/4
Work done by Q and R in one hour = 1/3
Work done by P and R in one hour = 1/2
Work done by R in one hour = 1/2- 1/4= 1/4
Work done by Q in one hour = 1/3- 1/4= 1/12
Therefore, time taken by Q to complete the work = 12 hours.

Free Tests

Free
Must Attempt

CBT-1 Full Mock Test 1

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

CBT-1 General Awareness Section Test 1

languageIcon English
  • pdpQsnIcon40 Questions
  • pdpsheetsIcon30 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RRB JE CBT-I’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
382k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow