Correct option is B
Work done by P, Q and R in one day = 1/3
Work done by R in one days = 1/3-(1/6+1/8)
= 1/3-((8+6)/48)
= (16-14)/48
= 1/24
Therefore, time taken to complete the work by R = 24
Efficiency of the work = 1/6: 1/8 : 1/24 = 4:3:1
Total wage = 3200
Wage paid to R = 3200×1/8=400