    P and Q can complete a job in 6 and 8 days individually. They both finish the job with the help of R in 3 days. How much wages are to be paid to R, if
    Question

    P and Q can complete a job in 6 and 8 days individually. They both finish the job with the help of R in 3 days. How much wages are to be paid to R, if the total wages are Rs. 3200?

    A.

    Rs. 375

    B.

    Rs. 400

    C.

    Rs. 1200

    D.

    Rs. 320

    Correct option is B


    Work done by P, Q and R in one day = 1/3
    Work done by R in one days = 1/3-(1/6+1/8)
    = 1/3-((8+6)/48)
    = (16-14)/48
    = 1/24
    Therefore, time taken to complete the work by R = 24
    Efficiency of the work = 1/6: 1/8 : 1/24 = 4:3:1
    Total wage = 3200
    Wage paid to R = 3200×1/8=400

    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB Group D Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB JE CBT-I’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    393k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow