Aaron can finish a work in 48 days and Brandon can do the same work in 96 days. On working together, they will complete the same work in how many days
Question

Aaron can finish a work in 48 days and Brandon can do the same work in 96 days. On working together, they will complete the same work in how many days?

A.

38

B.

36

C.

32  

D.

34

Correct option is C

Aaron's 1 day work = 1/48
Brandon's 1 day work = 1/96

Together work in 1 day

= 1/48 + 1/96

LCM = 96

= 2/96 + 1/96
= 3/96
= 1/32

Time required = 32 days

Free Tests

Free
Must Attempt

OSSSC RI, ARI, AMIN Full Mock Test : 01

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

OSSSC RI, ARI, AMIN 2025 Prelims Exam PYP (Held on 11-Nov-2025)

languageIcon English
  • pdpQsnIcon100 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon90 Mins
languageIcon English
Free
Must Attempt

Last Minute Revision Test: Odisha Budget

languageIcon English
  • pdpQsnIcon10 Questions
  • pdpsheetsIcon10 Marks
  • timerIcon6 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘OSSC CGL’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
416k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow