A can complete a piece of work in 18 days, and B can do it in 27 days. If they work together, how many days will they take to complete the work?
Question

A can complete a piece of work in 18 days, and B can do it in 27 days.
If they work together, how many days will they take to complete the work?

A.

10.8 days

B.

12 days

C.

11.25 days

D.

9 days

Correct option is A

Given
Time taken by A = 18 days
Time taken by B = 27 days

Formula Used
If A can do a work in x days and B can do it in y days, together they can complete it in  x×yx+y days.\frac{x \times y}{x + y} \ days.​​

Solution
Using the direct formula for combined work:
Time taken together = 18×2718+27 \frac{18 \times 27}{18 + 27}

Time taken together =  48645\frac{486}{45}​​
Time taken together = 10.8 days

Final Answer
So the correct answer is (a)

Free Tests

Free
Must Attempt

SSC GD Constable Exam Day Based Mock 1

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

SSC GD PYP (Held on 4 Feb 2025 S1)

languageIcon English
  • pdpQsnIcon80 Questions
  • pdpsheetsIcon160 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Mathematics Section Test 1

languageIcon English
  • pdpQsnIcon20 Questions
  • pdpsheetsIcon40 Marks
  • timerIcon25 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘SSC Selection Post (Matriculation)’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
416k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow