In a field 6 workers complete a task in 16 days. If this task is to be completed in 4 days, then how many workers will be required?
Question

In a field 6 workers complete a task in 16 days. If this task is to be completed in 4 days, then how many workers will be required?

A.

20

B.

18

C.

24

D.

28

Correct option is C

By using ,

x 16 = 4 x X
X = 6 x 16 / 4
X = 6 x 4
X = 24 workers

Free Tests

Free
Must Attempt

DSSSB PRT Full Mock - 01

languageIcon English
  • pdpQsnIcon200 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon120 Mins
languageIcon English
Free
Must Attempt

Educational Psychology & Pedagogy - 01

languageIcon English
  • pdpQsnIcon20 Questions
  • pdpsheetsIcon20 Marks
  • timerIcon15 Mins
languageIcon English
Free
Must Attempt

DSSSB PRT PYP Held on 7th March 2022 Shift 1

languageIcon English
  • pdpQsnIcon200 Questions
  • pdpsheetsIcon200 Marks
  • timerIcon120 Mins
languageIcon English

Similar Questions

test-prime-package

Access ‘RAJASTHAN REET’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow