arrow
arrow
arrow
For a project activity, the optimistic, the pessimistic and the most likely times are 4, 14 and 6 days respectively. Its average time is _________
Question

For a project activity, the optimistic, the pessimistic and the most likely times are 4, 14 and 6 days respectively. Its average time is _________

A.

10 days

B.

7 days

C.

12 days

D.

9 days

Correct option is B

PERT estimates the average time by considering three estimates: optimistic (O), pessimistic (P), and most likely (M).

The PERT average time (expected time) is calculated as:

Given:

  • Optimistic (O) = 4 days

  • Most likely (M) = 6 days

  • Pessimistic (P) = 14 days

Calculation:

Hence, the average time for the project activity is 7 days.

Information Booster:

  • The PERT technique uses a weighted average to account for uncertainty in activity durations.

  • Optimistic time (O) is the minimum time under ideal conditions.

  • Pessimistic time (P) is the maximum time assuming delays or difficulties.

  • Most likely time (M) is the best estimate assuming normal conditions.

  • The formula gives greater weight to the most likely time to reflect realistic expectations.

  • Expected time helps in project scheduling and critical path analysis.

  • PERT helps in managing projects with uncertain activity durations.

Free Tests

Free
Must Attempt

Basics of Education: Pedagogy, Andragogy, and Hutagogy

languageIcon English
  • pdpQsnIcon10 Questions
  • pdpsheetsIcon20 Marks
  • timerIcon12 Mins
languageIcon English
Free
Must Attempt

UGC NET Paper 1 Mock Test 1

languageIcon English
  • pdpQsnIcon50 Questions
  • pdpsheetsIcon100 Marks
  • timerIcon60 Mins
languageIcon English
Free
Must Attempt

Basics of Education: Pedagogy, Andragogy, and Hutagogy

languageIcon English
  • pdpQsnIcon10 Questions
  • pdpsheetsIcon20 Marks
  • timerIcon12 Mins
languageIcon English
test-prime-package

Access ‘UGC NET Management’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
368k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow