hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    For a project activity, the optimistic, the pessimistic and the most likely times are 4, 14 and 6 days respectively. Its average time is _________
    Question

    For a project activity, the optimistic, the pessimistic and the most likely times are 4, 14 and 6 days respectively. Its average time is _________

    A.

    10 days

    B.

    7 days

    C.

    12 days

    D.

    9 days

    Correct option is B

    PERT estimates the average time by considering three estimates: optimistic (O), pessimistic (P), and most likely (M).

    The PERT average time (expected time) is calculated as:

    Given:

    • Optimistic (O) = 4 days

    • Most likely (M) = 6 days

    • Pessimistic (P) = 14 days

    Calculation:

    Hence, the average time for the project activity is 7 days.

    Information Booster:

    • The PERT technique uses a weighted average to account for uncertainty in activity durations.

    • Optimistic time (O) is the minimum time under ideal conditions.

    • Pessimistic time (P) is the maximum time assuming delays or difficulties.

    • Most likely time (M) is the best estimate assuming normal conditions.

    • The formula gives greater weight to the most likely time to reflect realistic expectations.

    • Expected time helps in project scheduling and critical path analysis.

    • PERT helps in managing projects with uncertain activity durations.

    Free Tests

    Free
    Must Attempt

    Basics of Education: Pedagogy, Andragogy, and Hutagogy

    languageIcon English
    • pdpQsnIcon10 Questions
    • pdpsheetsIcon20 Marks
    • timerIcon12 Mins
    languageIcon English
    Free
    Must Attempt

    UGC NET Paper 1 Mock Test 1

    languageIcon English
    • pdpQsnIcon50 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon60 Mins
    languageIcon English
    Free
    Must Attempt

    Basics of Education: Pedagogy, Andragogy, and Hutagogy

    languageIcon English
    • pdpQsnIcon10 Questions
    • pdpsheetsIcon20 Marks
    • timerIcon12 Mins
    languageIcon English
    test-prime-package

    Access ‘UGC NET Management’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow