Correct option is B
PERT estimates the average time by considering three estimates: optimistic (O), pessimistic (P), and most likely (M).
The PERT average time (expected time) is calculated as:
Given:
Optimistic (O) = 4 days
Most likely (M) = 6 days
Pessimistic (P) = 14 days
Calculation:

Hence, the average time for the project activity is 7 days.
Information Booster:
The PERT technique uses a weighted average to account for uncertainty in activity durations.
Optimistic time (O) is the minimum time under ideal conditions.
Pessimistic time (P) is the maximum time assuming delays or difficulties.
Most likely time (M) is the best estimate assuming normal conditions.
The formula gives greater weight to the most likely time to reflect realistic expectations.
Expected time helps in project scheduling and critical path analysis.
PERT helps in managing projects with uncertain activity durations.