Correct option is C
Given:
C and D together can complete the work in 40 days.
C is 40% more efficient than D.
Solution:
Let the efficiency of D be x units/day.
Then, the efficiency of C = 1.4x units/day.
Combined efficiency of C and D = x + 1.4x = 2.4x units/day.
Time taken by C and D together to complete the work = 40 days.
Work = Efficiency × Time = 2.4x × 40 = 96x units.
Time taken by C alone=Efficiency of CTotal workTime taken by C alone=1.4x96x=1.496=14960=7480days.∴C alone can complete the work in approximately 7480days.