Correct option is A
Given:
Anjali's time = 40 days
Bipin's time = 60 days
They work on alternate days starting with Anjali.
Formula Used:
Work = Efficiency × Time
Solution:
Total Work = LCM(40, 60) = 120 units
Anjali's efficiency = = 3 units/day
Bipin's efficiency = = 2 units/day
In a 2-day cycle, work done = 3 + 2 = 5 units
Number of 2-day cycles to complete 120 units = = 24 cycles
Total days taken = 24 × 2 = 48 days
Final Answer
So the correct answer is (a)