    A man, a woman and a boy can do a work individually in 3, 4 and 12 days respectively. How many boys are to be employed to help 3 men and 4 women to fi
    Question

    A man, a woman and a boy can do a work individually in 3, 4 and 12 days respectively. How many boys are to be employed to help 3 men and 4 women to finish the work in 1/4 of a day?

    A.

    28

    B.

    20

    C.

    24

    D.

    12

    Correct option is C

    Given:
    A man can complete the work in 3 days.

    A woman can complete the work in 4 days.

    A boy can complete the work in 12 days.

    The work must be finished in 1/4 day.

    Concept Used:
    The amount of work done by one man, one woman, and one boy in 1 day is given by:

    Work by 1 man in 1 day=13 Work by 1 woman in 1 day=14 Work by 1 boy in 1 day=112\text{Work by 1 man in 1 day} = \frac{1}{3}\\\ \\\text{Work by 1 woman in 1 day} = \frac{1}{4}\\\ \\\text{Work by 1 boy in 1 day} = \frac{1}{12}

    Solution:

    The total work done by 3 men and 4 women in 1 day is:

    3×13+4×14=1+1=23 \times \frac{1}{3} + 4 \times \frac{1}{4} = 1 + 1 = 2​​

    The total work that must be completed in 1/4 day is:

    Work required=4 units per day\text{Work required} = 4 \, \text{units per day}​​

    The remaining work to be done by boys is:

    42=2 units4 - 2 = 2 \, \text{units}​​

    Let the number of boys be x .

    The work done by x boys in 1 day is:

    x×112x \times \frac{1}{12}​​

    Equating the work done by boys to the remaining work:

    x×112=2 x=2×12=24x \times \frac{1}{12} = 2\\\ \\x = 2 \times 12 = 24​​

    Therefore, 24 boys are needed to help 3 men and 4 women finish the work in 1/4 day.

    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB JE’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    368k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow