Correct option is B
Given:
Time taken by father to complete the work = 8 days
Time taken by son to complete the work = 7 days
Formula Used:
Let total work be 1.
Then work done 1 day =
Solution:
Father’s one day’s work =
Son’s one day’s work =
Father and Son’s one pair of day work together =
Total pair of days required to work =
Total days = = 6 days
Work left =
Work on 7th day
Work left =
Work done on 8th day =
Total time taken to complete the work =
Alternative Method:
Total work = Time Efficiency
Total work =LCM of 8 and 7 = 56
Efficiency of Father = = 7 units
Efficiency of Son== 8 units
Total efficiency of Father and Son for 2 days working on alternate days = 7+8 =15
Time required to completer the work =
Work left = 11 units
Work done on 7th day by father = 7 units
Work left = 11-7 = 4 units
Work done on 8th day =
Total time required by father and son working on alternate days =