hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    A father can complete a task in 8 days, while the son can do it in 7 days. If they work on alternate days, with the father starting, then in how many
    Question

    A father can complete a task in 8 days, while the son can do it in 7 days. If they work on alternate days, with the father starting, then in how many days will the task be completed?

    A.

    612\frac{1}{2}​​

    B.

    712\frac{1}{2}​​

    C.

    6

    D.

    7

    Correct option is B

    Given:

    Time taken by father to complete the work = 8 days

    Time taken by son to complete the work = 7 days

    Formula Used:

    Let total work be 1.

    Then work done 1 day =1Total time to work\frac{1}{Total\ time\ to\ work}​​

    Solution:

    Father’s one day’s work = 18 \frac{1}{8}​​

    Son’s one day’s work =17 \frac{1}{7}​​

    Father and Son’s one pair of  day work together =18+17 \frac{1}{8}+\frac{1}{7}​​

    =7+856=1556= \frac{7+8}{56}=\frac{15}{56}​​

    Total pair of days required to work =1556×3=4556 \frac{15}{56} \times 3 = \frac{45}{56}​​

    Total days =3×2 3\times 2​ = 6 days

    Work left =14556=1156 1 - \frac{45}{56} =\frac{11}{56}​​

    Work on 7th day =18= \frac{1}{8}​​

    Work left =115618=456=114 \frac{11}{56} - \frac{1}{8} =\frac{4}{56} = \frac{1}{14}​​

    Work done on 8th day = 11417=12\frac{\frac{1}{14}}{\frac{1}{7}} =\frac{1}{2}​​

    Total time taken to complete the work = 712days7\frac{1}{2}days​​

    Alternative Method:

    Total work = Time × \times​ Efficiency

    Total work =LCM of 8 and 7 = 56

    Efficiency of Father =568 \frac{56}{8}​ = 7 units

    Efficiency of Son=567 \frac{56}{7} ​= 8 units

    Total efficiency of Father and Son for 2 days working on alternate days = 7+8  =15

    Time required to completer the work = 5615=31115\frac{56}{15} =3 \frac{11}{15}​​

    Work left = 11 units

    Work done on 7th day by father = 7 units

    Work left = 11-7 = 4 units

    Work done on 8th day =48=12day \frac{4}{8} =\frac{1}{2}day​​

    Total time required by father and son working on alternate days = 7+12=712days7 + \frac{1}{2} =7\frac{1}{2} days​​

    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC UG Level PYP (Held on 7 Aug 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB NTPC’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    368k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow