Correct option is D
Given:
A can do of the work in 12 days.
B can do 20% of the work in 10 days.
C can do of the work in 8 days.
D can do of the work in 12 days.
Concept Used:
Time to complete the work
Solution:
A does of the work in 12 days.
Work rate of A (work per day)
Time to complete the work == 60 days
B does 20% (or ) of the work in 10 days.
Work rate of B =(work per day)
Time to complete the work =50 days
C does of the work in 8 days.
Work rate of C = (work per day)
Time to complete the work days
D does of the work in 12 days.
Work rate of D = (work per day)
Time to complete the work = = 60 days
Thus, C will complete the work first as they will finish in 48 days.