Correct option is B
Given:
A completes 25% of the task in 10 days
B completes 40% of the task in 40 days
C completes 31 of the task in 13 days
Solution:
A completes 25% of the task in 10 days
To complete 100% of the task
TimeA=25100×10 days=40 days
B completes 40% of the task in 40 days
To complete 100% of the task
TimeB=4040 days×100=100 days
C completes 31 of the task in 13 days
To complete 100% of the task
TimeC=3113 days=39 days
TimeA=40 days
TimeB=100 days
TimeC=39 days
C takes the least time to complete the task
C has the fastest speed to complete the task
Thus Option (b) is correct