Correct option is C
Given:
A can do the work in 20 days.
B can do the work in 30 days.
C can do the work in 60 days.
Solution:
A's work rate: work per day.
B's work rate: work per day.
C's work rate: work per day.
Work Done in Two Days:
On odd-numbered days (A and B work together):
Combined work rate =
On even-numbered days (A and C work together):
Combined work rate =
Total work in 2 days:
Work completed in 12 days (6 full 2-day cycles):
Remaining work after 12 days:
1−0.9=0.1
Work on the 13th day (odd, A + B):
Work done = =0.0833
Remaining work = 0.1 - 0.0833 = 0.0167
Time on the 14th day (even, A + C):
A + C work rate =
Time required = days
Total Time:
12days + 1day + 0.25day =13.25days ,
Thus, correct answer is (c)
Alternate Method:
Total work = Efficiency Time
LCM of (20, 30, 60) = total work = 60
Individual Efficiency of A = 3, B = 2 , C = 1
On Day 1 A+B work = 3 + 2 = 5 unit
On Day 2 A + C work = 3 + 1 = 4 unit
Total work on two days = 5 + 4 = 9 unit
So in 12 day work completed = 54 unit
on 13th day A + B work ,
Work completed = 54 + 5 = 59 unit
Remaining work = 60 - 59 = 1 unit
time taken by A + C =
Now, total time to complete the work = 13 days