hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    ​A, B and C can do a piece of work in 20, 30 and 60 days, respectively. A works every day. B assists A on all odd-numbered days, while C assists A on
    Question

    ​A, B and C can do a piece of work in 20, 30 and 60 days, respectively. A works every day. B assists A on all odd-numbered days, while C assists A on all even-numbered days. In how many days will the work be completed?

    A.

    131513\frac{1}{5}​​

    B.

    131313\frac{1}{3}​​

    C.

    131413\frac{1}{4}​​

    D.

    131213\frac{1}{2}​​

    Correct option is C

    Given:

    A can do the work in 20 days.

    B can do the work in 30 days.

    C can do the work in 60 days.

    Solution:

    A's work rate: 120\frac{1}{20} work per day.

    ​B's work rate: 130\frac{1}{30} work per day.

    ​C's work rate: 160\frac{1}{60} work per day.

    ​Work Done in Two Days: 

    On odd-numbered days (A and B work together):

    ​Combined work rate = 120+130=3+260=560=112\frac{1}{20} + \frac{1}{30} = \frac{3 + 2}{60} = \frac{5}{60} = \frac{1}{12}  

    ​On even-numbered days (A and C work together):

    ​Combined work rate = 120+160=3+160=460=115\frac{1}{20} + \frac{1}{60} = \frac{3 + 1}{60} = \frac{4}{60} = \frac{1}{15}  

    ​Total work in 2 days: 

    112+115=560+460=960=320 \frac{1}{12} + \frac{1}{15} = \frac{5}{60} + \frac{4}{60} = \frac{9}{60} = \frac{3}{20} 

    Work completed in 12 days (6 full 2-day cycles): 

    6×320=1820=0.9.6 \times \frac{3}{20} = \frac{18}{20} = 0.9.

    ​​Remaining work after 12 days:

    1−0.9=0.1

    ​Work on the 13th day (odd, A + B):

    Work done = 112\frac{1}{12} =0.0833

    Remaining work = 0.1 - 0.0833 = 0.0167

    ​Time on the 14th day (even, A + C):

    A + C work rate = 115\frac{1}{15} 

    ​Time required = 0.0167115=0.25\frac{0.0167}{\frac{1}{15}} = 0.25  days

    ​Total Time: 

    12days + 1day + 0.25day =13.25days , 131413 \frac{1}{4}

    Thus, correct answer is (c) 131413 \frac{1}{4} 

    Alternate Method: 

    Total work = Efficiency ×\times Time

    LCM of (20, 30, 60) = total work = 60  

    Individual Efficiency of A = 3, B = 2 , C = 1 

    On Day 1 A+B work = 3 + 2 = 5 unit 

    On Day 2 A + C work = 3 + 1 = 4 unit 

    Total work on two days = 5 + 4 = 9 unit 

    So in 12 day work completed = 54 unit 

    on 13th day A + B work , 

    Work completed = 54 + 5 = 59 unit 

    Remaining work = 60 - 59 = 1 unit 

    time taken by A + C = 14\frac{1}{4}  

    Now, total time to complete the work = 1314\frac 14 days​

    Free Tests

    Free
    Must Attempt

    CBT-1 Full Mock Test 1

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    RRB NTPC Graduate Level PYP (Held on 5 Jun 2025 S1)

    languageIcon English
    • pdpQsnIcon100 Questions
    • pdpsheetsIcon100 Marks
    • timerIcon90 Mins
    languageIcon English
    Free
    Must Attempt

    CBT-1 General Awareness Section Test 1

    languageIcon English
    • pdpQsnIcon40 Questions
    • pdpsheetsIcon30 Marks
    • timerIcon25 Mins
    languageIcon English

    Similar Questions

    test-prime-package

    Access ‘RRB NTPC’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    354k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow