Correct option is B
Given:
A can complete the work in 12 days
B can complete the work in 20 days
C can complete the work in 15 days
Working order: C (Day 1), B (Day 2), A (Day 3), C (Day 4), ...
Formula Used:
Work per cycle = C’s 1 day work + B’s 1 day work + A’s 1 day work
Number of full cycles =
Solution:
A’s 1 day work =
B’s 1 day work =
C’s 1 day work =
Work done in 3 days:
So, work done in 3 days =
Therefore, in 15 days (5 cycles), work done = = 1
Alternate Solution:
LCM of 12, 20, 15 = 60 units (assumed total work)
Work rates:
A = = 5 units/day
B = = 3 units/day
C = = 4 units/day
3-day cycle work:
Day 1 (C) = 4 units
Day 2 (B) = 3 units
Day 3 (A) = 5 units
Total per cycle = 4 + 3 + 5 = 12 units
Number of full 3-day cycles:
= 5 cycles
Total days = 5 × 3 = 15 days