Correct option is D
Given:
A works in 18 days and B works in 24 days
Solution:

Efficiency of A and B are 4 and 3 respectively
Work done by A in 2 days =
Now on 3rd Day, B both will work = 3 unit of work will be completed on 3rd day
Similarly pattern goes on,
So, In total 3 days = 11 unit of work completed
In next 3 unit of work completed
In next 18 days = 66 unit of work completed
Remaining work = 72- 66 = 6 unit
6 unit of work will be completed by A in
Total Time = 19 days