Correct option is A
Total work = 120 unit (LCM of 40, 30 and 60)
Efficiency of A and B together = 120/40=3 unit/day
Efficiency of B and C together = 120/30=4 unit/day
Efficiency of A = 120/60=2 unit/day
So, efficiency of B = 3 – 2 = 1 unit/day
And, efficiency of C = 4 – 1 = 3 unit/day
Increased efficiency of C = 3 +3×1/3=4 unit/day
Required days