arrow
arrow
arrow
A and B can complete a work in 10 days, while B and C can complete the same work in 15 days. A, B, and C together can finish the work in 6 days. In ho
Question

A and B can complete a work in 10 days, while B and C can complete the same work in 15 days. A, B, and C together can finish the work in 6 days. In how many days will A and C together complete the work?

A.

9 days

B.

7 days

C.

6 days

D.

8 days

Correct option is C


Solution:
Let total work = 30 units
(LCM of 10, 15, and 6)
Step 1: Find efficiencies
1. A + B finish work in 10 days → Efficiency of A + B = 30 / 10 = 3 units/day … (i.)
2. B + C finish work in 15 days → Efficiency of B + C = 30 / 15 = 2 units/day … (ii.)
3. A + B + C finish work in 6 days → Efficiency of A + B + C = 30 / 6 = 5 units/day … (iii.)
Step 2: Find individual efficiencies
From (iii.) − (ii.): A = 5 − 2 = 3 units/day
From (i.): B = (A + B) − A = 3 − 3 = 0 units/day
From (ii.): C = (B + C) − B = 2 − 0 = 2 units/day
Step 3: Efficiency of A + C
A + C = 3 + 2 = 5 units/day
Step 4: Time taken by A and C together
Time = Total Work ÷ Efficiency = 30 ÷ 5 = 6 days
Final Answer: 6 days

Similar Questions

test-prime-package

Access ‘DDA JE’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
353k+ students have already unlocked exclusive benefits with Test Prime!
test-prime-package

Access ‘DDA JE’ Mock Tests with

  • 60000+ Mocks and Previous Year Papers
  • Unlimited Re-Attempts
  • Personalised Report Card
  • 500% Refund on Final Selection
  • Largest Community
students-icon
353k+ students have already unlocked exclusive benefits with Test Prime!
Our Plans
Monthsup-arrow