hamburger menu
All Coursesall course arrow
adda247
reward-icon
adda247
    arrow
    arrow
    arrow
    A and B can complete a work in 10 days, while B and C can complete the same work in 15 days. A, B, and C together can finish the work in 6 days. In ho
    Question

    A and B can complete a work in 10 days, while B and C can complete the same work in 15 days. A, B, and C together can finish the work in 6 days. In how many days will A and C together complete the work?

    A.

    9 days

    B.

    7 days

    C.

    6 days

    D.

    8 days

    Correct option is C


    Solution:
    Let total work = 30 units
    (LCM of 10, 15, and 6)
    Step 1: Find efficiencies
    1. A + B finish work in 10 days → Efficiency of A + B = 30 / 10 = 3 units/day … (i.)
    2. B + C finish work in 15 days → Efficiency of B + C = 30 / 15 = 2 units/day … (ii.)
    3. A + B + C finish work in 6 days → Efficiency of A + B + C = 30 / 6 = 5 units/day … (iii.)
    Step 2: Find individual efficiencies
    From (iii.) − (ii.): A = 5 − 2 = 3 units/day
    From (i.): B = (A + B) − A = 3 − 3 = 0 units/day
    From (ii.): C = (B + C) − B = 2 − 0 = 2 units/day
    Step 3: Efficiency of A + C
    A + C = 3 + 2 = 5 units/day
    Step 4: Time taken by A and C together
    Time = Total Work ÷ Efficiency = 30 ÷ 5 = 6 days
    Final Answer: 6 days

    Similar Questions

    test-prime-package

    Access ‘DDA JE’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    test-prime-package

    Access ‘DDA JE’ Mock Tests with

    • 60000+ Mocks and Previous Year Papers
    • Unlimited Re-Attempts
    • Personalised Report Card
    • 500% Refund on Final Selection
    • Largest Community
    students-icon
    383k+ students have already unlocked exclusive benefits with Test Prime!
    Our Plans
    Monthsup-arrow