Correct option is A
Given:
A can complete the work = 60 days
B can complete work = 40 days
C can complete the work = 30 days
Solution:
Total work = LCM of (60, 40,30) = 120 unit
Efficiency of A =
Efficiency of B = unit/day
Efficiency of C = = 4 unit/day
3 days A and B did = (2+3) x 3 = 15 unit of work
Now C also joins.
All one day work now = 2+3+4 = 9 unit
Remaining work = 120-15 = 105 unit
they will do in =
= s .
= days taken to complete the task